Works on false ceiling and L Box had begun yesterday. We were pleasantly surprised to see the divider up as well with its niches done already. Though still in its raw form, it was nice to see it up already!
Completed works are:
- Gas pipe
- Rectification for aircon trunking in Master Bedroom (earlier it was extremely near the rear window)
"Visitor" to our flat resting on doorbell, near Household Shelter
Foyer - Divider made of gypsum board
Living Room - Part of L Box and pelmet
Bedroom 2 - casing for wiring will be covered by storage bench
Master Bedroom - casing for wiring here will also be covered by storage bench
Master Bedroom - False ceiling and partition wall for wardrobe
Master Bedroom - Partition wall for wardrobe
Master Bedroom - Back view of partition wall for wardrobe. There will be a sliding door installed.
Master Bedroom - Aircon trunking for rear window rectified